What is a change order? How to handle scope changes
A change order is a short written agreement that changes the scope, price or schedule of a contract that is already signed. It lets both sides agree extra or different work, and what it costs, before the work is done, so the final invoice holds no surprises.
Start with a change order form — free See the Word template
When you need one#
- The client asks for something the contract or statement of work does not cover.
- The client wants to remove part of the work, which should lower the price.
- Something outside your control, such as late content or a change in requirements, moves the deadline.
- The agreed approach turns out not to work and a different one costs more or less.
A useful test: if the change affects the price, the deadline or what you hand over, put it in a change order.
What a change order should include#
- A change order number and date, so several changes on one project stay in order.
- The original contract: its name, date and the parties.
- A description of the change in plain words.
- The items added, removed or changed, each with its cost or saving.
- The price change and the new contract total.
- How the change is paid, if not on the contract's normal terms.
- Any new completion date.
- A statement that everything else stays the same, and signatures from both sides before work starts.
Why it matters#
Most scope disputes start with "I thought that was included". A signed change order records exactly what was agreed and when. It also makes it easier to say yes to clients: you do not have to refuse extra work, you just price it.
Write the process into your contract#
Your contract or statement of work should say that changes need a written change order signed by both sides, how changes are priced (for example your hourly rate), and that the schedule moves with them. The change order then follows a process the client already agreed to.
Free templates
The free change order form lists each change with its amount, shows the price increase or decrease and the new total, and records any new completion date. Use it alongside the statement of work that defines the original scope. If a project ends instead of changing, the contract termination letter covers that.
General information, not legal advice.
Download a starter template#
More on freelancing and getting paid
- Freelance Contract: 10 Clauses to Include
- How to write a photography contract
- How to write a cleaning services contract
- What to include in a tutoring agreement
- How to write an independent contractor agreement
- How to write a purchase order (with an example)
- What to include in a statement of work (SOW)
- Quote vs Estimate vs Invoice: What to Send
- How to Write an Invoice (2026): 7-Step Checklist
- What Is a Kill Fee? (And How to Set One)
- Client Won't Pay? 7 Steps to Get Paid
- Demand Letter for Unpaid Invoices (Free)
- What is a credit note? When to issue one, what it must say
- What a VAT Invoice Must Include (UK)
- GST/HST Invoice Requirements (Canada)
- Tax Invoice Requirements (Australia: 7 Details)
- Bank Details on an Invoice (Stop Fraud Too)
Helpful?